Writing a Hardware Requirements Specification Engineers Can Use

A hardware requirements specification is the contract between the people who want a product and the people who build it. When it is vague, design decisions are made by default and the arguments happen at the end. When it is precise, the design has a target and the test plan almost writes itself. This article explains how to write requirements that are clear, measurable and complete enough to design against.

At a glance

Shall
The conventional word for a mandatory requirement; “should” marks a goal.
Measurable
Each requirement states a value, a condition and a tolerance that a test can check.
Unique ID
A permanent identifier, so each requirement can be traced to design and test.
Rationale
A short note on why the requirement exists, which helps when trade-offs arise.

The problem

Phrases such as “long battery life”, “rugged” or “low cost” feel like requirements but cannot be designed or tested. Each engineer fills the gap with an assumption, and the assumptions rarely agree.

The other common gap is missing conditions. A current limit means little without the supply voltage and temperature, and an accuracy figure is incomplete without the range over which it applies.

If a requirement cannot be tested, it is a hope, and hopes are expensive to discover at the end of a project.

Anatomy of a good requirement

A usable requirement states one thing, uses “shall”, gives a number with units and tolerance, and names the conditions: supply range, temperature, load or operating mode. “The device shall operate from 9 to 36 V DC across -20 to +60 °C ambient” can be designed and tested; “wide input range” cannot.

Separate what the product must do from how it does it. “Shall communicate with a phone within 10 m” leaves room for engineering; “shall use chip X” closes it, and belongs only where there is a real reason, recorded as the rationale.

What good looks like

Collect requirements by category: function, electrical, environmental, mechanical, regulatory, cost and lifetime. Gaps show up as empty categories.

Rewrite each one as a single measurable statement with conditions, an identifier and a rationale.

Review the specification with design and test engineers, and add a verification method to each requirement before design starts.

Vague and testable requirements
VagueTestable
Battery lifeLong battery lifeAt least 12 months at one report per hour
EnvironmentWorks outdoors-20 to +60 °C, IP65 enclosure
Power inputWide input range9 to 36 V DC, reverse polarity protected
ConnectivityWirelessBluetooth LE to a phone at 10 m line of sight
Illustrative rewrites. The testable version gives the designer a target and the tester a pass mark.
Requirement categories
CategoryExamplesOften forgotten
FunctionalInputs, outputs, modes, interfacesBehaviour on fault or power loss
ElectricalSupply range, current, accuracyStart-up, brown-out and transients
EnvironmentalTemperature, humidity, ingress, vibrationStorage and transport conditions
MechanicalSize, mass, connectors, mountingService access and cable routing
RegulatorySafety, EMC, radio, marketsLabelling and documentation
CommercialUnit cost, volume, product lifetimeComponent availability over the lifetime
A checklist of categories. An empty category is usually a gap, not an absence of requirements.

What it changes

Clear Targets

Engineers design to stated numbers instead of private assumptions.

Testable Results

Each requirement maps to a test that shows it was met.

Controlled Change

Identified requirements make the impact of a change visible.

Fewer Disputes

Everyone agrees at the start what finished means.

Where to go next

Keep the specification under revision control and record every change with a reason. It is a living document until the design is frozen.

Include the regulatory markets early. Standards for safety, emissions and radio bring their own requirements that shape the design.

Problems this prevents

  • Requirements that no test can check
  • Limits stated without operating conditions
  • Solutions specified in place of needs
  • Missing categories found late in the project